Submission Deadline and Committee and Board Meeting Schedule
The submission deadline for consideration at CPC/Board is typically the date of the Board meeting in the preceding month as outlined below. The Capital Programme Committee meets in the week preceding the board.
|
Submission deadline and Board Meeting schedule 20261 |
|
| Deadline for submission of IG deliverables for consideration at CPC/Board in the next month |
Board Meeting |
| Monday 8 December 2025 | Friday 9 January 2026 |
| Friday 16 January 2026 | Friday 20 February 2026 |
| Thursday 12 February 2026 | Thursday 12 March 2026 |
| Thursday 12 March 2026 | Friday 17 April 2026 |
| Friday 17 April 2026 | Friday 15 May 2026 |
| Friday 15 May 2026 | Thursday 11 June 2026 |
| Thursday 11 June 2026 | Thursday 9 July 2026 |
|
No meeting to be scheduled for August |
|
| Monday 24 August 2026 | Thursday 24 September 2026 |
| Thursday 24 September 2026 | Thursday 22 October 2026 |
| Thursday 22 October 2026 | Friday 20 November 2026 |
| Friday 20 November 2026 | Friday 18 December 2026 |
1 All dates are subject to change.
The material to be submitted
The material to be submitted for review is as follows:
- Final version of the relevant IGs deliverable seeking Approval Gate Approval
- Preliminary Business Case [PBC];
- Detailed Business Case, Project Execution Plan and Procurement Strategy [DBCPEPPS]; or
- Final Business Case [FBC].
- Final version of the documents which TAF also requires submission to the Approving Authority.
- Prior to PBC: Project/Programme Outline Document [POD] (only for schemes with estimated capital costs over €20m)
- Between the submissions of the POD and PBC: Longlist Assessment Report [LAR] (only for schemes with estimated total costs over €200m).
- Please bear in mind that the review will be conducted only on final versions, and not on Drafts. All legible intended appendices should also be submitted accompanying the full report.
- An executive summary report is required if the full document is greater than 10 pages. As a general guideline, the executive summary report should be no more than 10% in length of the full document.